You are managing two projects named Proj1 and Proj2. Proj1 has a milestone named Milestone1. Proj2 has a milestone named Milestone2. You need to create a relationship between both projects that…

The correct answer is C. Open Proj1 in Project Professional 2013 and create a deliverable for Milestone1. See the full explanation below for the reasoning.

Question

You are managing two projects named Proj1 and Proj2. Proj1 has a milestone named Milestone1. Proj2 has a milestone named Milestone2. You need to create a relationship between both projects that meets the following requirements:

  • Milestone2 depends on Milestone1.
  • The relationship provides visibility without affecting Milestone2's

schedule. What should you do?

Options

  • AOpen Project Professional 2013 and create a master project with Proj1 and Proj2 as
  • BOpen Project Professional 2013 and create a master project with Proj1 and Proj2 as
  • COpen Proj1 in Project Professional 2013 and create a deliverable for Milestone1.
  • DOpen Proj2 in Project Professional 2013 and create a deliverable for Milestone2.

How the community answered

(27 responses)
  • A
    4% (1)
  • B
    11% (3)
  • C
    81% (22)
  • D
    4% (1)