74-344 · Question #9
You are a manager for a project your team has been working on for many weeks. Your project is created as a Microsoft SharePoint task list project and is available in Project Center. You have…
The correct answer is B. Edit the project in Project Professional 2013 from the Project Center by clicking the icon of D. Edit the project in Project Professional 2013 by synching the SharePoint task list so you can. See the full explanation below for the reasoning.
Question
You are a manager for a project your team has been working on for many weeks. Your project is created as a Microsoft SharePoint task list project and is available in Project Center. You have established the work breakdown structure (WBS), predecessors, assignments, and all of the functionalities you can get from a SharePoint task list. However, the project has grown in detail, and managing 200 activities has become difficult in Project Web App (PWA). You need to ensure resources continue to report their progress in the same way. What are two possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.)
Options
- AActivate the Enterprise Project Features for the SharePoint site task list and edit the tasks in
- BEdit the project in Project Professional 2013 from the Project Center by clicking the icon of
- CActivate the Enterprise Project Features for the SharePoint site task list and edit the tasks in
- DEdit the project in Project Professional 2013 by synching the SharePoint task list so you can
How the community answered
(41 responses)- A7% (3)
- B73% (30)
- C20% (8)
Community Discussion
No community discussion yet for this question.