74-344 · Question #76
You are in the Project Management Office (PMO) for a company that uses Project Online to select portfolios for each business unit. The parameters used as cost constraints vary from department to…
The correct answer is A. Project Number B. Project Cost. See the full explanation below for the reasoning.
Question
You are in the Project Management Office (PMO) for a company that uses Project Online to select portfolios for each business unit. The parameters used as cost constraints vary from department to department, including Cost, CapEx, and Estimated Hours. You are responsible for providing the infrastructure to support the various constraints. You need to select a feasible method for employing cost constraints. Which two fields should you use? (Each correct answer presents part of the solution. Choose two.)
Options
- AProject Number
- BProject Cost
- CProject Text
- DProject Duration
How the community answered
(42 responses)- A81% (34)
- C7% (3)
- D12% (5)