Your organization is in the process of deploying Project Server 2013. Your business unit manages projects with different tools, such as Microsoft Excel and different versions of Project Professional…

The correct answer is B. Use Project Professional 2013 connected to Project Server 2013, open the standalone D. Use Project Professional 2013 connected to Project Server 2013, open the Excel file in. See the full explanation below for the reasoning.

Question

Your organization is in the process of deploying Project Server 2013. Your business unit manages projects with different tools, such as Microsoft Excel and different versions of Project Professional and Standard. Your business unit needs to upload and manage the projects in the new platform. You need to guarantee that the projects are uploaded in an efficient way while maintaining data integrity. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)

Options

  • AImport the projects from Excel spreadsheets to Project Professional 2013 by copying and
  • BUse Project Professional 2013 connected to Project Server 2013, open the standalone
  • CImport the projects from Project Standard 2013 to Project Web App (PWA) with the Import
  • DUse Project Professional 2013 connected to Project Server 2013, open the Excel file in

How the community answered

(46 responses)
  • A
    11% (5)
  • B
    72% (33)
  • C
    17% (8)