nerdexam
Microsoft

74-344 · Question #52

You are a project manager for an organization that uses Project Online. You create a resource plan to provide high level resource demand during the portfolio intake and selection process. Your…

The correct answer is A. Change the Calculate From setting on the resource plan. See the full explanation below for the reasoning.

Question

You are a project manager for an organization that uses Project Online. You create a resource plan to provide high level resource demand during the portfolio intake and selection process. Your project is now selected for detailed planning. You complete a detailed work breakdown structure (WBS). You need to remove the resource demand from the resource plan. What should you do?

Options

  • AChange the Calculate From setting on the resource plan.
  • BGo to Project Center and delete the resource plan.
  • CInactivate the resource plan.
  • DGo to Server Settings and delete the resource plan.
  • ESet the Publish flag to No on the resource plan.

How the community answered

(37 responses)
  • A
    81% (30)
  • B
    5% (2)
  • C
    3% (1)
  • D
    11% (4)

Community Discussion

No community discussion yet for this question.

Full 74-344 Practice