You are a project manager who uses Project Online. Your project is scheduled to run for at least 18 months. You create a schedule for the first six months, including estimated resource demand, using…

The correct answer is C. Create a resource plan and set the Resource Utilization to calculate from the project until a. See the full explanation below for the reasoning.

Question

You are a project manager who uses Project Online. Your project is scheduled to run for at least 18 months. You create a schedule for the first six months, including estimated resource demand, using Project Professional 2013. For planning purposes, you need to reserve proposed demand for the final 12 months. What should you do?

Options

  • ACreate new tasks in the project to represent the unplanned portion of the project.
  • BCreate a resource plan and enter the resource requirements for the final 12 months.
  • CCreate a resource plan and set the Resource Utilization to calculate from the project until a
  • DCreate new tasks in the project to represent the unplanned portion of the project.

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    8% (2)
  • C
    85% (22)
  • D
    4% (1)