74-344 · Question #38
Your company uses Project Professional 2013. An organization with project managers of varying expertise wants a simple, standard view that displays overall project status. You need an out-of-box…
The correct answer is C. Work Overview dashboard. See the full explanation below for the reasoning.
Question
Your company uses Project Professional 2013. An organization with project managers of varying expertise wants a simple, standard view that displays overall project status. You need an out-of-box function that provides the ability to assess current, baseline, and actual work for the project. Which view should you use?
Options
- AProject Overview dashboard
- BResource Allocation view
- CWork Overview dashboard
- DRelationship Diagram view
How the community answered
(25 responses)- A8% (2)
- B4% (1)
- C72% (18)
- D16% (4)