Microsoft
74-344 · Question #36
You are a project manager who uses Project Standard 2013. You have been told to build multiple project files for a program. You need to have all of your projects start with auto scheduled tasks by…
The correct answer is C. Under schedule options, set New tasks created to Auto Scheduled for all new projects. See the full explanation below for the reasoning.
Question
You are a project manager who uses Project Standard 2013. You have been told to build multiple project files for a program. You need to have all of your projects start with auto scheduled tasks by default. What should you do?
Options
- AUnder schedule options, set New tasks created to Auto Scheduled for each project.
- BUse the Task Mode field to change the first task to Auto Schedule, then copy down for all of
- CUnder schedule options, set New tasks created to Auto Scheduled for all new projects.
- DHighlight all of the tasks in your schedule and select the Auto Schedule button.
How the community answered
(54 responses)- A11% (6)
- B7% (4)
- C78% (42)
- D4% (2)
Community Discussion