You are a team member in an organization that uses Project Server 2013. Each week you report progress on multiple projects that are managed as Microsoft SharePoint task lists. You need to update…

The correct answer is B. My Tasks page in Newsfeed. See the full explanation below for the reasoning.

Question

You are a team member in an organization that uses Project Server 2013. Each week you report progress on multiple projects that are managed as Microsoft SharePoint task lists. You need to update task progress on multiple projects from one page. Which page should you use?

Options

  • ATasks page in Project Web App (PWA)
  • BMy Tasks page in Newsfeed
  • CTasks page in a Project site
  • DTimesheet page in Project Web App (PWA)

How the community answered

(39 responses)
  • A
    3% (1)
  • B
    74% (29)
  • C
    15% (6)
  • D
    8% (3)