You are an administrator in an organization that uses Project Server 2013. Single entry mode is disabled. Resources use the Tasks page in Project Web App (PWA) to report task progress. You need to…
The correct answer is C. Set the tracking method to hours of work done per period. See the full explanation below for the reasoning.
Question
You are an administrator in an organization that uses Project Server 2013. Single entry mode is disabled. Resources use the Tasks page in Project Web App (PWA) to report task progress. You need to ensure that resources have the ability to report work actuals per day. What should you do?
Options
- ASet the tracking method to actual work done and work remaining.
- BSet the tracking method to percent of work complete.
- CSet the tracking method to hours of work done per period.
- DEnable the option to allow users to define custom periods for task updates.
How the community answered
(31 responses)- A6% (2)
- B16% (5)
- C74% (23)
- D3% (1)