The IT department uses Project Online to analyze the projects they will execute the next year. Four projects with their respective priority and costs are shown in the exhibit. (Click the Exhibit…

The correct answer is B. The sum of Cost Estimate of Selected Projects will be 550k. D. The Portfolio Strategic Value will be of 44%. See the full explanation below for the reasoning.

Question

The IT department uses Project Online to analyze the projects they will execute the next year. Four projects with their respective priority and costs are shown in the exhibit. (Click the Exhibit button.) The team needs to get the most value from their portfolio, but some last minute restrictions could change their selection. A mutually inclusive dependency is added between the two CRM projects. A mutually inclusive dependency is also added between the two EPM projects. You need to assist the team in achieving the most value in their portfolio, given the constraints shown in the exhibit. You enforce the dependencies and recalculate the analysis. Which two statements become true? (Each correct answer presents part of the solution. Choose two.)

Exhibit

74-344 question #11 exhibit

Options

  • AThe Portfolio Strategic Value will be of 56%.
  • BThe sum of Cost Estimate of Selected Projects will be 550k.
  • CThe sum of Cost Estimate of Selected Projects will be 900k.
  • DThe Portfolio Strategic Value will be of 44%.

How the community answered

(47 responses)
  • A
    4% (2)
  • B
    85% (40)
  • C
    11% (5)