You are a program manager in the Project Management Office (PMO) of an organization that uses Project Server 2013. The Enterprise Gantt Chart is visible to all project managers. You plan to create a…

The correct answer is A. In Project Professional 2013, check-out the Enterprise Global template, modify the. See the full explanation below for the reasoning.

Question

You are a program manager in the Project Management Office (PMO) of an organization that uses Project Server 2013. The Enterprise Gantt Chart is visible to all project managers. You plan to create a new project enterprise custom field to show information about schedule variance. You need to include this new field in the Enterprise Gantt Chart in Project Professional 2013 so that all project managers of actual and future projects who use this view can see this field by default. What should you do?

Options

  • AIn Project Professional 2013, check-out the Enterprise Global template, modify the
  • BCreate a Project Center view named Enterprise Gantt Chart with the new project enterprise
  • CModify the Project Information project details page by adding the new project enterprise
  • DIn Project Professional 2013, create a blank project, add a new view named Enterprise

How the community answered

(46 responses)
  • A
    80% (37)
  • B
    7% (3)
  • C
    11% (5)
  • D
    2% (1)