Question
You manage a project for which the team has not delivered all of the story points committed to in a previous sprint. You want to define the amount of work the team can commit to for the next sprint of the project. What should you do?
Options
- AReview the sprint burndown to define the amount of work.
- BReview the team velocity to define the amount of work
- CAllow the product owner to define the amount of work.
- DReview capacity of the team to define the amount of work.