70-498 · Question #66
Your development team uses Scrum as its process framework and utilizes the Microsoft Solution Framework (MSF) for Agile Software Development 6.0 process template. Your product owner requests making…
The correct answer is C. Create user story work items for the request. See the full explanation below for the reasoning.
Question
Your development team uses Scrum as its process framework and utilizes the Microsoft Solution Framework (MSF) for Agile Software Development 6.0 process template. Your product owner requests making an internal system public. The request is top priority for the next sprint. You need to determine if the team can commit to the request for the next sprint. What should you do?
Options
- ACreate user story work items for the request.
- BCreate user story work items for the request.
- CCreate user story work items for the request.
- DCreate product backlog item work items for the request.
How the community answered
(26 responses)- A8% (2)
- B4% (1)
- C73% (19)
- D15% (4)