70-498 · Question #61

As the manager of a mission-critical application development project, you oversee the technical delivery of a software application. The project has not met any of its milestones, and there are early…

The correct answer is B. Analyze the complexity of the work in progress (WIP) and determine if there is any way to E. Identify and remove wait times in the development cycle. See the full explanation below for the reasoning.

Question

As the manager of a mission-critical application development project, you oversee the technical delivery of a software application. The project has not met any of its milestones, and there are early signs that what requested. Each iteration is taking approximately three weeks longer to finish than available is being produced is not what the stakeholders have was scheduled. No more resources will be made available. You need to reduce the cycle time without impacting commitments. Which two actions should you perform? (Each correct answer presents a complete solution. Choose two.)

Options

  • AReduce (or remove) cycle requirements for quality assurance (QA) and user acceptance
  • BAnalyze the complexity of the work in progress (WIP) and determine if there is any way to
  • CWork with your technical leads to remove any features from the end product that, on paper,
  • DCreate a technical oversight committee that will meet and review all project work and identify
  • EIdentify and remove wait times in the development cycle.

How the community answered

(39 responses)
  • A
    8% (3)
  • B
    74% (29)
  • C
    3% (1)
  • D
    15% (6)

Community Discussion

No community discussion yet for this question.