70-498 · Question #59
You manage a development team for a group of stakeholders that are physically remote from your development center. Stakeholders have blocked out dates and times on their schedules for your team. The…
The correct answer is B. Develop a series of iterative proofs of concept that reflect a partial delivery of requirements D. Add a primary stakeholder to your team as the product owner. See the full explanation below for the reasoning.
Question
You manage a development team for a group of stakeholders that are physically remote from your development center. Stakeholders have blocked out dates and times on their schedules for your team. The stakeholders are concerned that several of the project requirements will not meet their needs due to changing market conditions. You need to ensure that the following requirements are met:
- Your team is doing effective and efficient work.
- The work is meeting the needs of the business.
- The project's timeline is not at risk.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
Options
- AInstitute a policy of sign-offs for each requirement and design document.
- BDevelop a series of iterative proofs of concept that reflect a partial delivery of requirements
- CInstruct the team to create a comprehensive set of design documents for each layer of the
- DAdd a primary stakeholder to your team as the product owner.
How the community answered
(32 responses)- A9% (3)
- B78% (25)
- C13% (4)