70-498 Question #139: Real Exam Question with Answer & Explanation

The correct answer is A. Use the TFS administration console to add a field product backlog item WIT. B. Use the process template manager, and download the process template. Use the process. See the full explanation below for the reasoning.

Question

Your company uses Microsoft Visual Studio Team Foundation Server (TFS). You have permissions to modify work items. The current product backlog item WIT is functioning properly. However, the product owner needs to track each product backlog item's estimated value to the company. The company has a system that ranks value by using a grading system of A-E. The company needs a new field in the product backlog item that captures this system and only allows A-E. You need to modify the product backlog item WIT on the server. Which two actions should you perform? Each correct answer presents a complete solution.

Options

  • AUse the TFS administration console to add a field product backlog item WIT.
  • BUse the process template manager, and download the process template. Use the process
  • CUse the process template editor to add a field to the existing WIT.
  • DUse witadmin.exe to download the XML Edit the XML to add the field, and use witadmin to upload