In which service component of the security operate phase would an escalation notification plan be used?

The correct answer is B. Incident or Problem Management. See the full explanation below for the reasoning.

Question

In which service component of the security operate phase would an escalation notification plan be used?

Options

  • AProject Management
  • BIncident or Problem Management
  • COperations Setup
  • DChange Management

How the community answered

(43 responses)
  • A
    2% (1)
  • B
    84% (36)
  • C
    5% (2)
  • D
    9% (4)