Which two of these activities are included in the operations plan development service component in the security design phase? (Choose two.)
The correct answer is A. Review Documentation C. Operational Design Development. See the full explanation below for the reasoning.
Question
Which two of these activities are included in the operations plan development service component in the security design phase? (Choose two.)
Options
- AReview Documentation
- BOperations Implementation for Security
- COperational Design Development
- DPresent Implementation and Operation Statement of Work
- EHold Project Kickoff Meeting
How the community answered
(52 responses)- A73% (38)
- B4% (2)
- D17% (9)
- E6% (3)