650-575 · Question #26
Which service component is typically performed prior to the handover to a customer operations organization?
The correct answer is B. Acceptance Testing. See the full explanation below for the reasoning.
Question
Which service component is typically performed prior to the handover to a customer operations organization?
Options
- ASystems Integration
- BAcceptance Testing
- CSkill Assessment
- DProject Closeout
- ESecurity Check
How the community answered
(41 responses)- B83% (34)
- C10% (4)
- D5% (2)
- E2% (1)