512-50 · Question #318

You are just hired as the new CISO and are being briefed on all the Information Security projects that your section has on going. You discover that most projects are behind schedule and over budget…

The correct answer is C. Verify resources. See the full explanation below for the reasoning.

Question

You are just hired as the new CISO and are being briefed on all the Information Security projects that your section has on going. You discover that most projects are behind schedule and over budget. Using the best business practices for project management you determine that the project correctly aligns with the company goals and the scope of the project is correct. What is the NEXT step?

Options

  • AReview time schedules
  • BVerify budget
  • CVerify resources
  • DVerify constraints

How the community answered

(31 responses)
  • A
    10% (3)
  • B
    3% (1)
  • C
    84% (26)
  • D
    3% (1)