512-50 · Question #317
You are just hired as the new CISO and are being briefed on all the Information Security projects that your section has on going. You discover that most projects are behind schedule and over budget…
The correct answer is A. Scope of the project. See the full explanation below for the reasoning.
Question
You are just hired as the new CISO and are being briefed on all the Information Security projects that your section has on going. You discover that most projects are behind schedule and over budget. Using the best business practices for project management you determine that the project correct aligns with the company goals. What needs to be verified FIRST?
Options
- AScope of the project
- BTraining of the personnel on the project
- CTimeline of the project milestones
- DVendor for the project
How the community answered
(32 responses)- A84% (27)
- B3% (1)
- C9% (3)
- D3% (1)