nerdexam
EC-Council

512-50 · Question #319

The new CISO was informed of all the Information Security projects that the organization has in progress. Two projects are over a year behind schedule and over budget. Using best business practices…

The correct answer is A. Verify the scope of the project. See the full explanation below for the reasoning.

Question

The new CISO was informed of all the Information Security projects that the organization has in progress. Two projects are over a year behind schedule and over budget. Using best business practices for project management you determine that the project correctly aligns with the company goals. Which of the following needs to be performed NEXT?

Options

  • AVerify the scope of the project
  • BVerify the regulatory requirements
  • CVerify technical resources
  • DVerify capacity constraints

How the community answered

(25 responses)
  • A
    84% (21)
  • B
    4% (1)
  • C
    8% (2)
  • D
    4% (1)

Community Discussion

No community discussion yet for this question.

Full 512-50 Practice