500-440 · Question #88
Which statement about the Cisco UCCE solution in the virtualized environment is true?
The correct answer is D. Spec-based virtualized servers based on Intel E5 26xx cpu family at speed 2.40 GHz is supported. Option D is correct because Cisco UCCE's virtualization policy supports spec-based servers (not just Cisco UCS hardware) provided they meet defined hardware requirements - specifically, servers using the Intel Xeon E5-26xx CPU family at 2.40 GHz or faster. This gives…
Question
Which statement about the Cisco UCCE solution in the virtualized environment is true?
Options
- AVMware NIC teaming whether in active-active or active-standby configuration on the UCS B/C
- BNexus 1000V virtual distributed switch can be used but only for 500 agent deployment model
- CCisco UCS VIC can be used on UCS C series TRC models
- DSpec-based virtualized servers based on Intel E5 26xx cpu family at speed 2.40 GHz is supported
How the community answered
(61 responses)- A7% (4)
- B3% (2)
- C8% (5)
- D82% (50)
Explanation
Option D is correct because Cisco UCCE's virtualization policy supports spec-based servers (not just Cisco UCS hardware) provided they meet defined hardware requirements - specifically, servers using the Intel Xeon E5-26xx CPU family at 2.40 GHz or faster. This gives organizations flexibility to deploy UCCE on third-party hardware that matches Cisco's published specifications.
Why the distractors are wrong:
- A is false because Cisco UCCE does not support active-active NIC teaming on UCS B/C series - only active-standby is permitted. Presenting both as valid is the trap.
- B is false because the Nexus 1000V virtual distributed switch is not restricted to 500-agent deployments; imposing that arbitrary limit makes the statement incorrect.
- C is false because Cisco UCS VIC (Virtual Interface Card) is not supported on UCS C series TRC (Tested Reference Configuration) models - TRC configurations use standard NICs, not VIC adapters.
Memory tip: Think "D = Defined specs" - Cisco opens UCCE virtualization to non-UCS hardware as long as the server meets defined CPU specifications (Intel E5-26xx at 2.40 GHz). If a choice puts an artificial restriction on something (like "only 500 agents" or "active-active allowed"), treat it as a red flag that it's wrong.