While evaluating a new hardware rollout plan before deployment, which standards should you review to ensure that the hardware met certain environmental design guidelines?
The correct answer is D. NEBS. See the full explanation below for the reasoning.
Question
While evaluating a new hardware rollout plan before deployment, which standards should you review to ensure that the hardware met certain environmental design guidelines?
Options
- ANAS
- BCOBIT
- CITIL@
- DNEBS
- EeTOM
How the community answered
(29 responses)- A3% (1)
- B3% (1)
- C14% (4)
- D72% (21)
- E7% (2)