350-060 · Question #89
A rollout plan from engineering has been sent to the NOC for deployment. Part of the plan involves a complex software upgrade to a network element. The method of procedure provided by engineering is…
The correct answer is D. after the method of procedure is completed. See the full explanation below for the reasoning.
Question
A rollout plan from engineering has been sent to the NOC for deployment. Part of the plan involves a complex software upgrade to a network element. The method of procedure provided by engineering is nearly 100 individual steps long. Where do you expect to find backout procedures to be specified?
Options
- Aafter each step that causes a change to the network
- Bafter every 20 (+/- 5) steps
- Cafter the midway point
- Dafter the method of procedure is completed
- Eboth after the midway point and after the method of procedure is completed
How the community answered
(31 responses)- A3% (1)
- B3% (1)
- D84% (26)
- E10% (3)