Which three factors should you consider when recommending a maintenance window to execute a rollout plan that is received from engineering? (Choose three.)
The correct answer is A. service level agreements D. time of day E. customer impact. See the full explanation below for the reasoning.
Question
Which three factors should you consider when recommending a maintenance window to execute a rollout plan that is received from engineering? (Choose three.)
Options
- Aservice level agreements
- Bnetwork capacity management
- Ckey performance indicators
- Dtime of day
- Ecustomer impact
How the community answered
(31 responses)- A81% (25)
- B13% (4)
- C6% (2)