You are working as a project manager in your organization. You are nearing the final stages of project execution and looking towards the final risk monitoring and controlling activities. For your…

The correct answer is C. Requested changes. See the full explanation below for the reasoning.

Question

You are working as a project manager in your organization. You are nearing the final stages of project execution and looking towards the final risk monitoring and controlling activities. For your project archives, which one of the following is an output of risk monitoring and control?

Options

  • AQuantitative risk analysis
  • BRisk audits
  • CRequested changes
  • DQualitative risk analysis

How the community answered

(52 responses)
  • A
    15% (8)
  • B
    4% (2)
  • C
    71% (37)
  • D
    10% (5)