Which methodology is a method to analyze the involved tasks in completing a given project, especially the time needed to complete each task, and identifying the minimum time needed to complete the…
The correct answer is C. PERT. See the full explanation below for the reasoning.
Question
Which methodology is a method to analyze the involved tasks in completing a given project, especially the time needed to complete each task, and identifying the minimum time needed to complete the total project?
Options
- ACPM
- BGantt
- CPERT
- DFP
How the community answered
(48 responses)- A8% (4)
- B17% (8)
- C71% (34)
- D4% (2)