You work as a project manager for TYU project. You are planning for risk mitigation. You need to identify the risks that will need a more in-depth analysis. Which of the following activities will…
The correct answer is A. Qualitative analysis. See the full explanation below for the reasoning.
Question
You work as a project manager for TYU project. You are planning for risk mitigation. You need to identify the risks that will need a more in-depth analysis. Which of the following activities will help you in this?
Options
- AQualitative analysis
- BEstimate activity duration
- CQuantitative analysis
- DRisk identification
How the community answered
(44 responses)- A84% (37)
- B5% (2)
- C2% (1)
- D9% (4)