Avaya
3101 · Question #52
Which action should be completed prior to installing a new service pack on Communication manager (CM)?
The correct answer is B. Stop CMM if enabled. See the full explanation below for the reasoning.
Question
Which action should be completed prior to installing a new service pack on Communication manager (CM)?
Options
- AStop Cm
- BStop CMM if enabled
- CDeactivate any existing service pack
- DDo a save translation/reset system 4
How the community answered
(64 responses)- A9% (6)
- B81% (52)
- C3% (2)
- D6% (4)
Community Discussion
No community discussion yet for this question.