The correct answer is B. Perform full CM backup and CMM backup (all categories) at CM SMI at 5 PM.. See the full explanation below for the reasoning.

Question

It is 10 AM and you are responsible For maintaining a Communication Manager System. Your local electric company just Informed you that there will be a power outage between 6-10 PM tonight. At 1PM you are expected to add equipment, extensions, and mailbox for four temporary workers who are working onsite through tomorrow afternoon. Your regular CM (full) backup is scheduled for 9 PM but it does not include CMM. What information should you save, at what Interface, and when to ensure that there are no problems tomorrow morning?

Options

  • ASave translations at the SAT at 5 PM
  • BPerform full CM backup and CMM backup (all categories) at CM SMI at 5 PM.
  • CPerform full CM backup from the CM SMI at 5 PM.
  • DPerform full CM backup at the CM SMI immediately
  • ESave translations at the SAT and perform a CMM backup at the C MM SMI at 2 PM.