220-1102 · Question #726
An administrator's change was approved by the change management review board. Which of the following should the administrator do next?
The correct answer is C. Implement the change. In the change management lifecycle, once a change request has been reviewed, tested, and formally approved by the change advisory board (CAB), the next step is implementation. Risk analysis and testing should have already been completed before the change was submitted for…
Question
An administrator's change was approved by the change management review board. Which of the following should the administrator do next?
Options
- APerform risk analysis.
- BAssign a change coordinator.
- CImplement the change.
- DVerify testing results.
How the community answered
(40 responses)- B3% (1)
- C95% (38)
- D3% (1)
Explanation
In the change management lifecycle, once a change request has been reviewed, tested, and formally approved by the change advisory board (CAB), the next step is implementation. Risk analysis and testing should have already been completed before the change was submitted for approval. Assigning a change coordinator is an earlier administrative step. Verifying testing results is also done prior to approval. Approval is the green light to proceed - so implementation is what comes next.