The correct answer is B: Rollback plan. The change management document that includes how to uninstall a patch is called the "rollback plan". The rollback plan is a document that outlines the steps that should be taken to undo a change that has been made to a system. In the case of a patch, the rollback plan would inclu

Operational Procedures

Question

Which of the following change management documents includes how to uninstall a patch?

Options

  • APurpose of change
  • BRollback plan
  • CScope of change
  • DRisk analysis

Explanation

The change management document that includes how to uninstall a patch is called the "rollback plan". The rollback plan is a document that outlines the steps that should be taken to undo a change that has been made to a system. In the case of a patch, the rollback plan would include instructions on how to uninstall the patch if it causes problems or conflicts with other software.

Topics

#Change management#Rollback plan#Patch management#IT documentation

Community Discussion

No community discussion yet for this question.

Full 220-1102 PracticeBrowse All 220-1102 Questions