Which of the following is NOT a requirement when validating, receiving, unpacking, and planning access route and space requirements for Exadata Database Machine?

The correct answer is E. Oracle Exadata Rack may only be installed on raised floor environments. Exadata Database Machine is a pre-configured and pre-tuned hardware and software system designed to run Oracle Database, it can be installed on raised floor environments, but also on concrete or tile floors. Oracle Exadata Database Machine X9M Implementation Essentials states…

Exadata X9M System Installation and Configuration

Question

Which of the following is NOT a requirement when validating, receiving, unpacking, and planning access route and space requirements for Exadata Database Machine?

Options

  • AThe entire access route to the installation site should be free of raised-pattern flooring that can
  • B914mm of space required above the rack height is required for maintenance access.
  • CThe incline of any access route ramp must be less than or equal to 6 degrees.
  • DAll four leveling and stabilizing feet should be raised and out of the way prior to moving the rack.
  • EOracle Exadata Rack may only be installed on raised floor environments.
  • FA conditioned space is required to remove the packaging material to reduce particles before

How the community answered

(60 responses)
  • C
    3% (2)
  • D
    2% (1)
  • E
    93% (56)
  • F
    2% (1)

Explanation

Exadata Database Machine is a pre-configured and pre-tuned hardware and software system designed to run Oracle Database, it can be installed on raised floor environments, but also on concrete or tile floors. Oracle Exadata Database Machine X9M Implementation Essentials states that Exadata racks are designed to be installed on flat surfaces, not raised floor environments. It is not required to install the rack on raised floor environments. Additionally, the other options listed are all requirements for validating, receiving, unpacking, and planning access route and space requirements for Exadata Database Machine.