1Z0-902 · Question #19
An Exadata X9M-2 Elastic Rack with 4 Database Servers and 8 HC Storage Servers and 3-phase 24kVA PDUs is being installed in a Data Center. However, the Data Center is only providing enough power for…
The correct answer is C. The installation cannot proceed until two power feeds are available per PDU. In order for an Exadata X9M-2 Elastic Rack to be installed, two power feeds are required for each of the three-phase 24kVA PDUs. A single cable from each PDU will not be enough to power the rack, and neither a splitter cable nor rearrangement of the power cables from the…
Question
An Exadata X9M-2 Elastic Rack with 4 Database Servers and 8 HC Storage Servers and 3-phase 24kVA PDUs is being installed in a Data Center. However, the Data Center is only providing enough power for a single cable from each PDU. Which statement is correct?
Options
- AA splitter cable can be used to provide power to all PDU cables.
- BThe power cables from the servers to the PDUs can be rearranged inside the rack following OECA
- CThe installation cannot proceed until two power feeds are available per PDU.
- DThe installation can go ahead, no change is required.
How the community answered
(57 responses)- A2% (1)
- B4% (2)
- C89% (51)
- D5% (3)
Explanation
In order for an Exadata X9M-2 Elastic Rack to be installed, two power feeds are required for each of the three-phase 24kVA PDUs. A single cable from each PDU will not be enough to power the rack, and neither a splitter cable nor rearrangement of the power cables from the servers to the PDUs will be able to provide sufficient power for the system. Therefore, the installation cannot proceed until two power feeds are available per PDU. For more information about power requirements for Exadata X9M-2 Elastic Racks, refer to the Oracle Exadata Database Machine X9M Implementation Essentials official text book and