1Z0-902 · Question #19

1Z0-902 Question #19: Real Exam Question with Answer & Explanation

Sign in or unlock 1Z0-902 to reveal the answer and full explanation for question #19. The question stem and answer options stay visible for context.

Question

An Exadata X9M-2 Elastic Rack with 4 Database Servers and 8 HC Storage Servers and 3-phase 24kVA PDUs is being installed in a Data Center. However, the Data Center is only providing enough power for a single cable from each PDU. Which statement is correct?

Options

  • AA splitter cable can be used to provide power to all PDU cables.
  • BThe power cables from the servers to the PDUs can be rearranged inside the rack following OECA
  • CThe installation cannot proceed until two power feeds are available per PDU.
  • DThe installation can go ahead, no change is required.