1Z0-565 · Question #50
When changing a Bill of Material through an Engineering Change Order, which three selections are true?
The correct answer is A. Removal of the Bill of Material Is not allowed through ECO. C. Substitute Items are copied from the old component to the new component. E. The Work Order Parts List related to the parent item is updated. See the full explanation below for the reasoning.
Question
When changing a Bill of Material through an Engineering Change Order, which three selections are true?
Options
- ARemoval of the Bill of Material Is not allowed through ECO.
- BThe system updates the effectively dates in the Bill of Material.
- CSubstitute Items are copied from the old component to the new component.
- DThe drawing revision level is updated.
- EThe Work Order Parts List related to the parent item is updated
How the community answered
(40 responses)- A75% (30)
- B8% (3)
- D18% (7)