1Z0-565 · Question #17
Which are created as a result of running the UBE MRP-MPS Requirements Planning (R3482)?
The correct answer is C. Work Orders. See the full explanation below for the reasoning.
Question
Which are created as a result of running the UBE MRP-MPS Requirements Planning (R3482)?
Options
- AAction Messages
- BWarning Messages
- CWork Orders
- DPurchase Order
- ETime Series
How the community answered
(54 responses)- A2% (1)
- B4% (2)
- C76% (41)
- D13% (7)
- E6% (3)
Community Discussion
No community discussion yet for this question.