The customer needs to create Work Orders to support the manufacturing process. Which three statements about Work Orders are true?

The correct answer is A. Category Code values from the parent's Item Branch Plant Record can be loaded into a Work B. Item-based shrink will increase the quantities of components on the parent Work Order's parts E. Manually copying a Bill of Material to make a parts list will advance the status of the work order. See the full explanation below for the reasoning.

Question

The customer needs to create Work Orders to support the manufacturing process. Which three statements about Work Orders are true?

Options

  • ACategory Code values from the parent's Item Branch Plant Record can be loaded into a Work
  • BItem-based shrink will increase the quantities of components on the parent Work Order's parts
  • CThe Lot Number can be assigned any time up to and Including- Work Order completion.
  • DManually copying a Routing to make a Routing specific to a Work Order will advance the status of
  • EManually copying a Bill of Material to make a parts list will advance the status of the work order.

How the community answered

(20 responses)
  • A
    80% (16)
  • C
    5% (1)
  • D
    15% (3)