According to the recommended training for this exam, when does the Project Manager assume responsibility for the project profitability?

The correct answer is D. When the client requests it. See the full explanation below for the reasoning.

Question

According to the recommended training for this exam, when does the Project Manager assume responsibility for the project profitability?

Options

  • AWhen the Project Manager accepts it during the transaction from sales to delivery
  • BNever
  • CAt the start of the sales cycle
  • DWhen the client requests it

How the community answered

(22 responses)
  • A
    5% (1)
  • B
    14% (3)
  • C
    5% (1)
  • D
    77% (17)

Community Discussion

No community discussion yet for this question.