Oracle
1Z0-466 · Question #78
For our purposes, what is the most important work product produced by the project manager as prescribed by OUM Manage?
The correct answer is A. Project management Plan. See the full explanation below for the reasoning.
Question
For our purposes, what is the most important work product produced by the project manager as prescribed by OUM Manage?
Options
- AProject management Plan
- BProject Resource Plan
- CProject Estimate
- DProject Budget
- EProject Bid
How the community answered
(55 responses)- A75% (41)
- B4% (2)
- C5% (3)
- D15% (8)
- E2% (1)
Community Discussion