106 · Question #70
Fill in the blanks: Portfolio office members should NOT have the responsibility of _____.
The correct answer is C. Direct delivery of projects and programmes. Portfolio office members operate at a governance and oversight level, not an execution level - making C correct because direct delivery of projects and programmes is the responsibility of project/programme managers and their teams, not the portfolio office. Option A is incorrect
Question
Fill in the blanks: Portfolio office members should NOT have the responsibility of _____.
Options
- AApproving the portfolio strategy and delivery plan
- BChampioning the portfolio within the organisation
- CDirect delivery of projects and programmes
- DActively participating in creating an energetic culture in project teams.
How the community answered
(35 responses)- A3% (1)
- C91% (32)
- D6% (2)
Explanation
Portfolio office members operate at a governance and oversight level, not an execution level - making C correct because direct delivery of projects and programmes is the responsibility of project/programme managers and their teams, not the portfolio office. Option A is incorrect because approving portfolio strategy and delivery plans is precisely a core portfolio office governance function. Option B is wrong because championing the portfolio across the organisation is a key advocacy role the portfolio office plays to secure buy-in and alignment. Option D is a distractor because while it sounds unusual, portfolio offices do contribute to organisational culture by modelling good practices and fostering engagement.
Memory tip: Think of the portfolio office as the "board room, not the engine room" - they direct, approve, and champion, but never get their hands dirty with day-to-day delivery. If a responsibility sounds like it belongs to a project manager on the ground, it's not the portfolio office's job.