nerdexam
PeopleCert

106 · Question #70

Fill in the blanks: Portfolio office members should NOT have the responsibility of _____.

The correct answer is C. Direct delivery of projects and programmes. Portfolio office members operate at a governance and oversight level, not an execution level - making C correct because direct delivery of projects and programmes is the responsibility of project/programme managers and their teams, not the portfolio office. Option A is incorrect

Understanding the roles and responsibilities within portfolio management

Question

Fill in the blanks: Portfolio office members should NOT have the responsibility of _____.

Options

  • AApproving the portfolio strategy and delivery plan
  • BChampioning the portfolio within the organisation
  • CDirect delivery of projects and programmes
  • DActively participating in creating an energetic culture in project teams.

How the community answered

(35 responses)
  • A
    3% (1)
  • C
    91% (32)
  • D
    6% (2)

Explanation

Portfolio office members operate at a governance and oversight level, not an execution level - making C correct because direct delivery of projects and programmes is the responsibility of project/programme managers and their teams, not the portfolio office. Option A is incorrect because approving portfolio strategy and delivery plans is precisely a core portfolio office governance function. Option B is wrong because championing the portfolio across the organisation is a key advocacy role the portfolio office plays to secure buy-in and alignment. Option D is a distractor because while it sounds unusual, portfolio offices do contribute to organisational culture by modelling good practices and fostering engagement.

Memory tip: Think of the portfolio office as the "board room, not the engine room" - they direct, approve, and champion, but never get their hands dirty with day-to-day delivery. If a responsibility sounds like it belongs to a project manager on the ground, it's not the portfolio office's job.

Topics

#Portfolio office roles#Portfolio governance#Project delivery separation#Portfolio management scope

Community Discussion

No community discussion yet for this question.

Full 106 Practice