Veeam
VMCE2021 · Question #392
All VMs in a data center need to be failed over to a disaster recovery site due to an approaching hurricane. Which failover method would ensure that changes made to the original VMs, after the…
The correct answer is B. Planned failover. See the full explanation below for the reasoning.
Question
All VMs in a data center need to be failed over to a disaster recovery site due to an approaching hurricane. Which failover method would ensure that changes made to the original VMs, after the scheduled replication jobs, are copied to the disaster recovery site?
Options
- AFailover plan
- BPlanned failover
- CReplica failover
- DFailover
How the community answered
(36 responses)- A11% (4)
- B78% (28)
- C6% (2)
- D6% (2)
Community Discussion