A company has replicated their critical application VMs to a second data center in another region. Their key application includes two database VMs and three application VMs. For proper operation…

The correct answer is A. Use a failover plan. https://helpcenter.veeam.com/docs/backup/vsphere/failover_plan.html?ver=110 In a failover plan, you set the order in which VMs must be processed and time delays for VMs.

Replication

Question

A company has replicated their critical application VMs to a second data center in another region. Their key application includes two database VMs and three application VMs. For proper operation, the database VMs need to start before the application VMs. What needs to be configured in Veeam to prepare for a disaster recovery situation?

Options

  • AUse a failover plan
  • BUse a planned failover
  • CUse Instant VM Recovery
  • DUse on-click failover

How the community answered

(43 responses)
  • A
    81% (35)
  • B
    5% (2)
  • C
    2% (1)
  • D
    12% (5)

Explanation

https://helpcenter.veeam.com/docs/backup/vsphere/failover_plan.html?ver=110 In a failover plan, you set the order in which VMs must be processed and time delays for VMs.