A company needs to maintain and verify backups at a secondary site to meet the following requirements: RTO of two hours, RPO of 12 hours, four weeks retention. Which of the following backup copy job…

The correct answer is B. Periodic backup copy job, scheduled for a 12-hour interval, with 56 restore points to retain. Based on RPO of 12 hours, they have 2 restore point per day, over 7 days of the week and 4 weeks retention --- 2x7x4=56 RPO

Backup

Question

A company needs to maintain and verify backups at a secondary site to meet the following requirements: RTO of two hours, RPO of 12 hours, four weeks retention. Which of the following backup copy job configurations meets these requirements?

Options

  • APeriodic backup copy job, scheduled for a two-hour interval, with 56 restore points to retain
  • BPeriodic backup copy job, scheduled for a 12-hour interval, with 56 restore points to retain
  • CPeriodic backup copy job, scheduled for a two-hour interval, with 112 restore points to retain
  • DPeriodic backup copy job, scheduled for a 12-hour interval, with 112 restore points to retain

How the community answered

(34 responses)
  • A
    12% (4)
  • B
    79% (27)
  • C
    6% (2)
  • D
    3% (1)

Explanation

Based on RPO of 12 hours, they have 2 restore point per day, over 7 days of the week and 4 weeks retention --- 2x7x4=56 RPO

Topics

#backup copy job#RPO#retention#periodic copy