A current state analysis is a project phase that is carried out to validate the end of a project.

The correct answer is B. False. A current state analysis gives an architect a way to examine the road ahead. Any oversights at this stage could have major implications for the project later on. By ensuring that the current state analysis is completed thoroughly, you can prevent many potential problems.

Create a Design for a vSphere 5.x Infrastructure

Question

A current state analysis is a project phase that is carried out to validate the end of a project.

Options

  • ATrue
  • BFalse

How the community answered

(51 responses)
  • A
    25% (13)
  • B
    75% (38)

Explanation

A current state analysis gives an architect a way to examine the road ahead. Any oversights at this stage could have major implications for the project later on. By ensuring that the current state analysis is completed thoroughly, you can prevent many potential problems.

Topics

#current state analysis#project lifecycle#design process