An implementation plan should contain _____________.
The correct answer is A. a milestone plan. An implementation plan gives all members of a project team a level of understanding of the technical approach of a project, the number of phases, major tasks in each phase, and the correct order for completing the tasks.
Create a Design for a vSphere 5.x Infrastructure
Question
An implementation plan should contain _____________.
Options
- Aa milestone plan
- Brisks, assumptions, and dependencies on the activities in the implementation plan
- Corder
How the community answered
(37 responses)- A70% (26)
- B22% (8)
- C8% (3)
Explanation
An implementation plan gives all members of a project team a level of understanding of the technical approach of a project, the number of phases, major tasks in each phase, and the correct order for completing the tasks.