The correct answer is B. False. A requirement is a definable and measurable project item. It must be part of the delivery, and its removal cannot be justified.
Question
If a vendor best practice details configuration that would not meet a project requirement, a solution should ignore that requirement.
Options
- ATrue
- BFalse
Explanation
A requirement is a definable and measurable project item. It must be part of the delivery, and its removal cannot be justified.