nerdexam
Broadcom-VMware

VDCD510 · Question #127

A well-thought-out request for change document contains __________. (Choose three)

The correct answer is A. configuration based on a known vendor based best practice B. an implementation plan C. a verification process. An implementation plan gives all members of a project team a level of understanding of the technical approach of a project, the number of phases, major tasks in each phase, and the correct order for completing the tasks.

Create a Design for a vSphere 5.x Infrastructure

Question

A well-thought-out request for change document contains __________. (Choose three)

Options

  • Aconfiguration based on a known vendor based best practice
  • Ban implementation plan
  • Ca verification process
  • Da change summary

How the community answered

(31 responses)
  • A
    84% (26)
  • D
    16% (5)

Explanation

An implementation plan gives all members of a project team a level of understanding of the technical approach of a project, the number of phases, major tasks in each phase, and the correct order for completing the tasks.

Topics

#change management#RFC#implementation plan#verification process

Community Discussion

No community discussion yet for this question.

Full VDCD510 Practice