VDCD510 · Question #127
A well-thought-out request for change document contains __________. (Choose three)
The correct answer is A. configuration based on a known vendor based best practice B. an implementation plan C. a verification process. An implementation plan gives all members of a project team a level of understanding of the technical approach of a project, the number of phases, major tasks in each phase, and the correct order for completing the tasks.
Create a Design for a vSphere 5.x Infrastructure
Question
A well-thought-out request for change document contains __________. (Choose three)
Options
- Aconfiguration based on a known vendor based best practice
- Ban implementation plan
- Ca verification process
- Da change summary
How the community answered
(31 responses)- A84% (26)
- D16% (5)
Explanation
An implementation plan gives all members of a project team a level of understanding of the technical approach of a project, the number of phases, major tasks in each phase, and the correct order for completing the tasks.
Topics
#change management#RFC#implementation plan#verification process