Tibco
TB0-123 · Question #43
You wish to insert an activity into an ActiveMatrix BusinessWorks process. Which TIBCO Designer menu should you use?
The correct answer is B. Resources. See the full explanation below for the reasoning.
Question
You wish to insert an activity into an ActiveMatrix BusinessWorks process. Which TIBCO Designer menu should you use?
Options
- AProject
- BResources
- CEdit
- DPalettes
How the community answered
(25 responses)- A4% (1)
- B76% (19)
- C12% (3)
- D8% (2)
Community Discussion